|
Alternate
Methods to Resolve Contract Disputes
Copyright,
Hill International, Inc., 2000
Ever
increasing financial pressures experienced by today's municipalities
make capital improvement and construction projects seem insurmountably
risky. Unforeseen disputes
among the project participants - designers, contractors and
subcontractors - can cause massive schedule delays and cost
overruns. Such disputes
often arise over the liability for a specific problem.
If not checked, these disputes can lead to costly and
time-consuming litigation, leaving municipal managers with unfinished
projects and skyrocketing costs to complete them.
Generally,
most construction-related disputes and schedule delays involved three
issues:
·
Differing
Site Conditions - conditions at the work site that are different
than anticipated or shown on design drawings and other project
documentation. A utility
line not shown on drawings, or an abnormally high content of rock in
soil at the site are two examples of differing site conditions.
·
Changes
in Scope of Work - a differentiation in the amount of work or
tasks needed to complete the project.
·
Changes
in scope can be the result of several factors, including changes deemed
necessary by the designer, contractor, or municipality.
Changes in scope also can result from unforeseen factors
encountered during the design and construction processes.
·
Unexpected
Delaying Events – Weather, labor problems, loss of funding and
unanticipated delays in permit approvals each are examples of unexpected
events that can delay a construction project.
Disputes
often involve who's at fault for the above-referenced changes, whether
the changes could have been anticipated, or who should have anticipated
them. Such disputes often
can be mitigated, however, with proper, proactive steps taken at the
beginning of a capital project, well before design and construction have
begun.
First,
a partnership between the municipality, architect/engineer and
contractor must be established on the basis of risk sharing and a
commitment to resolve disputes equitably and expediently.
In
recent years, new techniques have been introduced to do just that
‑ prevent, manage and resolve construction project disputes and
claims. Alternate Dispute
Resolution or (ADR) when used proactively can help resolve disputes
outside of the courtroom and help keep capital projects running
smoothly.
ADR:
RX FOR ADVERSARIAL ILLNESS
Dispute
prevention and dispute resolution must be employed during each stage of
the construction project ‑ from concept and design through
construction and occupancy. Ideally,
the best time to settle a dispute at the least cost to the parties and
with the least impact on the project, is at the time the issue is
raised. Options for
resolving disputes via ADR include:
1.
Negotiation among the parties involved in the dispute
2.
Mediation of the dispute using an independent mediator
3.
A dispute review board
4.
Binding arbitration, using guidelines of the American Arbitration
Association
5.
Partnering
NEGOTIATION
Equitable
negotiation is crucial. During
negotiation, recognize the adage that a fair settlement beats the heck
out of a good lawsuit." A
timely examination and amicable confrontation of a problem will greatly
improve the chances of its resolution.
Also, don't ignore a problem or postpone attempts to negotiate.
Both sides should exhibit good faith in their discussions to
facilitate a quick settlement. Remember
that negotiation requires preparation, a willingness to “give and
take,” and the need to leave personality conflicts at home.
In addition, recognize that you're part of a team. The roles of the project "owner" or municipality,
engineer, architect, project manager and contractor are interrelated.
Everyone involved in the capital project must play a part in
preventing, mitigating and resolving claims.
MEDIATION
When
negotiations fail, engage an independent mediator acceptable to both
sides who can assist the parties with a decision.
Ideally, an independent mediator should be selected by all
parties before work begins and, more importantly, before disputes arise.
The
key to the success of mediation is that the mediator be a neutral and
objective third party, and that he or she not be interested in the
outcome of the settlement, but only in a successful settlement.
DISPUTE
REVIEW BOARD
Dispute
Review Boards are relatively new entities, set up to review claims and
other disputes and render decisions about their validity. Usually, parties involved in the capital project present the
issues to a three-person panel that is established at the beginning of a
project to render a binding decision on each dispute as it arises.
Each party chooses a member of the board.
The two board members chosen then select a third member, with the
cost of the time of the individuals shared equally by the parties in the
contract. Since the board
members normally are chosen during the first 30 days of the project,
they have an opportunity to become familiar not only with the project,
but also with the documents and the parties to the contract.
Any dispute that is not settled by negotiation within 30 calendar
days is then referred to the review board for a hearing within another
15 days. The board then
conducts a hearing and normally makes a decision on the disputes within
15 days thereafter. However,
if the issue in dispute is crucial to the progress of the work, the
parties can agree on an expedited hearing and decision.
Industry representatives have reported that dispute review boards
can be highly successful. Statistics
indicate that of 100 recent cases sent referred to dispute review
boards, 98 were resolved there; only two cases proceeded to arbitration
and/or litigation. The 100
cases studied involved more than $6 billion in construction.
ARBITRATION
Arbitration
is the most frequently used and most standardized ADR procedure.
The American Institute of Architects (AIA) and the Associated
General Contractors of America (AGC), and the American Arbitration
Association (AAA) have standardized, published guidelines for
arbitration. Arbitration is
becoming increasingly common as more and more construction contracts
require mandatory binding arbitration of all disputes within a
designated period. Other
contracts call for arbitration at the discretion of the parties.
Although
the American Arbitration Association has a standard set of rules to
guide the arbitration procedure, the process is flexible and can be
jointly modified by both parties. For
example, each party involved in the dispute can pick its own arbitrator,
and the two selected arbiters then choose a third.
Under American Arbitration Association rules, however, arbiters
must be chosen from an approved AAA list. The parties can also agree to
certain voluntary discovery of documents and depositions of witnesses.
Although awards made by arbitrators or arbitration panels do not
usually provide the reasons or the findings in fact for the award, the
parties may be able to agree at the beginning about the nature of the
award decision. Once the
arbiters are selected, the arbitration progresses much like a trial,
often with a binding decision. Arbitration
procedures and a panel of arbiters should be agreed upon well before
work on your capital project begins, and disputes arise.
COMPARING
THE OPTIONS
With
mediation and arbitration, the parties consent to the process either at
the time the dispute arises or by signing the contract which contains
that provision.
·
Litigation,
however, is non-consensual ‑ any party can sue without the other
side's consent.
·
Mediation
and arbitration are flexible; the parties can agree to the procedures.
·
Litigation
is rigid, in that the rules within the court have already been
established.
·
Mediation
is non-judgmental, in that the mediator does not render a decision or an
award.
·
Arbitration
and litigation are judgmental in that binding decisions and/or awards
are rendered.
·
Litigation
produces a decision that usually can be appealed to a higher court.
·
Arbitration
provides for a final award with no appeal. ‑ Mediation, however,
is settlement-oriented and encourages the parties to reach a mutually
acceptable agreement.
·
Mediation
can end successfully with a written agreement between the parties for
the record.
·
Arbitration
usually results in an award, without a decision or findings of fact.
‑ Litigation produces a final decision, as well as findings of
fact and law.
·
Mediation
usually takes a relatively short amount of time and can be accomplished
in a matter of weeks.
·
Arbitration
and litigation may take much longer.
In fact, arbitration can take several months, and litigation up
to two years.
·
The
mediator's fees are usually split among the parties.
·
Arbitration
may require fees to be paid to three arbitration panelists, and also to
the AAA or other sponsoring organizations.
Litigation usually results in extensive legal costs for both
sides, as well as court fees.
PARTNERING
Partnering
is one of the most proactive ways to resolve disputes.
The basis of partnering is an understanding that all parties
benefit from a successful project, and that disputes only undermine that
success.
Partnering,
often established via an agreement at the start of a project, is based
on trust between the parties and constant communication to keep all of
the parties informed.
The
municipality architect/engineer the contractor usually enter into a
partnership agreement before work begins, wherein they sign a pledge to
assist each other in providing a successful project that is completed on
time and within budget. That pledge should include an agreed-upon effort to prevent
disputes before they occur and to continuously work toward eliminating
any adversarial relationship between the parties.
In
addition, partnering can only succeed with the support of each of the
parties' top management. That
support must include dispute resolution training, procedures for open
and consistent communication, and a commitment to risk sharing.
Partnering among all of the project participants also fosters a
sense of ownership of the mission and a stake in the success of a
project.
CHOOSING
AN ADR METHOD THAT' RIGHT FOR YOU
The
nature and magnitude of problems on previous capital projects may help
you decide which method of Alternative Dispute Resolution will fit your
needs. But, whether you
choose partnering, mediation or arbitration, that choice should be made
before you begin design and construction.
Procedures for dispute resolution should be established and
agreed upon early. And,
follow-through is essential to ensuring that the procedures are being
properly and consistently used.
As
municipal expenditures and funding applications become increasingly
scrutinized, avoiding time-consuming and costly litigation has become an
imperative. ADR can be an
effective tool for resolving disputes before they drain precious
financial and manpower resources, and place your long-debated capital
project at risk.
|