|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 9, No. 8, December 2007
Inside This Issue:
-
Attorneys Fees Recovery
Granted by Court
-
Building Information Modeling: The Wave of the
Future?
-
Surety Cannot Maintain Negligence
Action against A/E for Alleged Failure to Adequately Inspect and
Supervise Contractor’s Work
________________________
The
Construction SuperConference is in its 22nd year is recognized as the
preeminent legal construction conference. With the guidance of the
Advisory Board and the expertise and feedback from past participants and
long-time supporters of the conference, a program has been established
that will provide insight into some of the most complex legal and
business issues facing the construction industry.
This year the conference has been organized into 4 tracks:
Legal and Institutional, Business Related Issues, Contracts and
Management, and Industry Specific. In addition there are three plenary
session presentations, a breakfast session, and, for the first time,
"deep dive" workshops. The workshops, offered on Friday
afternoon, are an opportunity for attendees to get into very interactive
sessions that will spend time on very specific and focused topics,
strategies, services, or technologies that affect our industry. For an
example, a session on e-discovery may have panelists and experts
discussing the benefits, objectives, and case studies with regards to
e-discovery. The workshop will then discuss deeper issues with regards
to how you can implement e-discovery in your firm.
_________
Article
1
__________
Attorneys
Fees Recovery Granted by Court
By:
Nancy Zabala Graham
The California Court of
Appeal in the third appellate district recently affirmed the award of
almost $200,000 in attorney fees pursuant to a "prevailing
party" attorneys' fees provision in a contract. What makes this
case interesting is the fact that the property owner, who was awarded
his attorneys' fees, was not in contract with the subcontractor who was
ordered to pay the fees. The Court based its award on a contract between
the general contractor and subcontractor and found that the owner was an
intended third party beneficiary to that contract.
Vincent Loduca, Jr. v. George Polyzos (2007) 153
Cal.
App. 4th 334.
In 1989, Vincent Loduca,
the project owner, retained MCM Builders to act as the general
contractor to build his custom home. MCM, in turn, hired subcontractor
QMC to manufacture and install custom cabinetry in the new home. The
subcontract between MCM and QMC included a clause which stated that the
prevailing party in any litigation arising out of the subcontract would
be awarded its attorneys' fees.
Although QMC was directly
in contract with MCM, Loduca paid for some of the subcontractor's
services directly. In addition, toward the end of the project, Loduca
and QMC entered into a separate agreement, where QMC agreed to deliver
certain remaining components and Loduca agreed to pay $10,000 on
delivery. When Loduca received the cabinets he noticed numerous problems
with them and asked his bank to stop payment on the check sent to QMC.
QMC then removed all of the cabinetry from the home without the owner's
permission and litigation ensued. QMC filed a complaint against Loduca
for recovery of unpaid amounts and Loduca filed a cross complaint for
breach of contract, among other things.
The trial court entered
judgment in favor of Loduca and awarded $65,000 in damages. At a
subsequent hearing, the trial court awarded attorneys' fees to Loduca
pursuant to the contract between MCM and QMC in the amount of $190,350.
QMC appealed, claiming the court erred by awarding Loduca attorneys'
fees because Loduca was not a party to the contract between QMC and MCM
and therefore should not benefit from the attorneys' fees clause.
The court held that the
homeowner was in fact "an intended third party beneficiary"
who could enforce the subcontract and request attorneys' fees. A third
party beneficiary, although not a party to the contract, may be entitled
to enforce a contract if it proves that the contracting parties intended
to benefit the third party with the contract.
In Loduca's case, the court
concluded that Loduca was an intended beneficiary of the subcontract and
therefore able to enforce the attorneys' fees provision for several
reasons. First, the subcontract's "reference" line identified
Loduca as the owner. Second, the subcontract stated the cabinetry was to
be built according to plans developed for Loduca's home. Third, the
contract contained a broad attorneys' fees clause which did not specify
who could collect the attorneys' fees if they prevailed. The court thus
applied this broad provision to extend to any court action that arose
out of the contract even if was brought by a third party.
QMC argued the separate
agreement between Loduca and QMC demonstrated the parties did not intend
for Loduca to be able to recover attorneys' fees because this agreement
did not contain an attorneys' fees provision. However, the court
disagreed and held the QMC-Loduca agreement did not state that it
superseded the MCM-QMC agreement but it simply changed the terms of
payment and imposed additional penalties.
In addition, the court
based its decision on the close relationship between the subcontractor
and the property owner. Loduca made a separate agreement and paid QMC
directly. The court held that the alteration by the QMC-Loduca agreement
to the original contract effectively made Loduca a party to the
contract, thereby entitling and burdening him with the attorneys' fees
provision. The court concluded that in these circumstances, where such a
close relationship exists between the contracting parties and the third
party beneficiary, the contracting parties intended for the owner to
have a right of enforcement of the prevailing party attorneys' fees
clause.
A few lessons may be
learned from this case. First, all construction participants should be
acutely aware of any prevailing party attorneys' fees clauses in their
contracts. These provisions can vastly increase a party's exposure and
most insurance policies do not cover their contractually agreed upon
transfer of risk. In order to avoid potential liability to a third
party, contracts should specify the parties who can enforce the
prevailing party clause. Good drafting techniques can assist in avoiding
this type of third party liability. Further, all construction
participants should always be aware of the established contractual
relationships and their associated chains of communication. Deviating
from the norms could unknowingly subject you to the terms, and
obligations of a contract between others.
About the Author: Nancy Zabala Graham is a law clerk Gordon & Rees, LLP;
275 Battery Street, Suite 2000;
San Francisco,
CA
94111; Phone: (415) 986-5900. Website: http://www.gordonrees.com.
The
Construction Practice Group at Gordon & Rees represents design
professionals, developers, contractors, subcontractors and suppliers.
Projects with which the group has had experience includes site
developments, residential developments, commercial buildings, hospitals,
jails, airports, bridges, dams and power plants. The group has
experience with all aspects of construction-related litigation,
including design or construction defects; delay, disruption and
acceleration; earth movement; job-site injury and many others.
This
article is published in ConstructionRisk.com Report, Vol. 9, No. 8.
__________
Article
2
__________
Building
Information Modeling: The Wave of the Future?
By: Gary
Prather – Travelers
Building Information Modeling (BIM) promises to reshape the future
design – and the way design professionals do business, but these basic
risk management considerations should be taken into account to determine
if BIM is right for you. To boldly go where no man has gone before. Such
was the mission of the Starship Enterprise and its crew in the hit
sci-fi TV series Star Trek. And such is the mission of the design
technique known as Building Information Modeling (BIM).
BIM is a design method
using computer technology to represent building components and systems,
both functionally and graphically, and allows for the ongoing
coordination among various parties. Design information for every aspect
of the project is input into one database, so it can be accessed by
various people. It also allows for additional drawings and information
to be added to the database and enhances the coordination process, as it
allows, for example, the architect’s drawings and shop drawings to be
integrated into one coordinated model.
The result? When fully
implemented, BIM will enable multiple users to collaborate in the design
process. Indeed, BIM is on the mind of every owner, project/construction
manager, and builder across the country. And while human transporters à
la Star Trek are not yet a reality, BIM promises to reshape the face
of future design.
How Does BIM Work?
BIM essentially leverages
3-Dimensional computer-aided design and drafting (CADD) by incorporating
component-rich databases for all relevant design elements. Thus, rather
than having only two-dimensional drawings to work from, designers and
contractors can have access to all information, being able to readily
flip through the models to glean information from the various designs.
Through the collection and integration of all pertinent design
information, a more coordinated, efficient, and error-free design
process results.
As the use of this
technology grows, 3-D BIM models should ultimately replace today’s
plans and specifications, serve to streamline the cumbersome submittal
process, and transform today’s solo-driven design-construction
industry into a more collaborative process that benefits from the skills
and expertise of all of the participants in the design process.
Is BIM The Way To
Go?
As the design-construction
industry grapples with cyber design, design professionals will face a
barrage of questions about the new model. For example, designers may
question how BIM will change the way they do business, and whether their
instruments of service change from paper files to electronic media or
from two-dimensional drawings to three-dimensional models.
Questions may also arise
about what level of financial investment will be required in order to
access the new technology and, perhaps more importantly, what the
return/payback period for BIM will be. Designers will also want to know
whether their liability risks are going to change, and if so, whether
their insurance will also change in order to be consistent with their
needs.
While there are more
questions today than answers, before implementing BIM, design
professionals need to consider some basic risk management ideas to
determine if BIM is right for them. Some of those considerations
include:
Process Changes – BIM requires new business models, hardware,
software, and human capital. The costs and risks associated with the
hardware and software investments may pale in comparison to those costs
involved in hiring and training staff to manage BIM-driven project
delivery. Younger design professionals will embrace BIM, while older,
experienced staff will likely struggle with the move from CADD to BIM.
Meanwhile, firm leadership will need to balance the cultural change to
BIM to ensure the new technology does not replace practical design
experience.
Management Practices – New business processes require new management
practices. Managing BIM’s fluidity and blurred lines of authority and
accountability demand more control and understanding of the technology
driving the model. Project managers need to become skilled in all
aspects of the firm’s selected BIM platform. CADD is a drawing tool
that is relatively easy to manage without understanding the technology.
BIM is a complex design tool that requires an in-depth understanding of
the software to effectively manage and satisfy design accountability.
Contract Considerations – For the most part, professional associations
are taking a wait-and-see approach to BIM. BIM-related service
agreements, for the foreseeable future, will be authored by owners,
design professionals, and their legal counsel. Design firms are
cautioned against executing BIM agreements without first having their
legal counsel and professional liability carrier review the agreements
for insurability.
Going forward, the industry
will develop a better appreciation of how the risks should be
distributed among the design-construction team, including the owner,
designer, contractor, subcontractors, and suppliers. To realize the
potential benefits of BIM, the risks need to be shared equally, as
information also needs to be shared.
Equal Considerations – Inputting a manufacturer’s proprietary
software information into a BIM model has the potential of creating a
closed specification. Designers need to use care in building the model
so that the Building Information Model they use is not limited to a
single source, unless an owner specifically requests this.
Software Warranties – Software manufacturers are careful not to
over-promise or guarantee the adequacy of their products, which puts
design professionals squarely at odds with the project owners who, in
order to fully reap BIM’s benefits, want everyone on the project to
have access to the BIM. Thus, the coordination process through BIM could
mean the industry will struggle with this risk vs. reward debate until
all parties work together to develop new contract forms that clearly
address, assign, and share risk equitably.
Design Creep – The ease by which design changes in BIM can be
made increases the risk of design and scope of services. Information,
including design elements, is input into the BIM database, and the
database interconnects elements of a building design. So when a change
is made to one aspect of the design, for example, all related designs
would be reconfigured accordingly. The urge to use BIM’s flexibility
to make change upon change right up to and including bidding and
construction must be aggressively managed and purposefully constrained.
While making changes in BIM may be easy, budgets and design-construction
schedules are not as pliable.
Blurring of Design
Responsibility – BIM may make some design professionals
uncomfortable and others downright fearful when it comes to affixing
their seal to the design documents. What control over the design will be
relinquished to the software providers, contractors, subcontractors,
manufacturers, and suppliers? Where is the line between the
designer-of-record and the other entities supplying input to the model?
Can the designer-of-record demonstrate his/her control over the design
without being a “BIM Expert”? Without adequate supervision, is BIM
similar to the risks associated with off shore outsourcing? Until these
questions are answered, the industry can expect that BIM models will be
used as design tools, and the two-dimensional drawings and
specifications will continue to serve as the contract documents that
everyone relies upon.
A Higher Standard of Care? – BIM touts its ability to eliminate design
conflicts, reduce errors, and limit omissions. But a question remains
– will the use of BIM raise the standard of care? Will design
professionals using BIM be held to a standard of care equal to
perfection or something very close to it? It will be a long while before
there is case law addressing these questions. In the short term,
designers need to be proactive in defining and reinforcing the concept
that the standard of care for BIM-delivered projects as being the same
as the standard of care for conventionally-delivered designs.
Model Control &
Maintenance – BIM project teams will need strong individuals
to manage model input and changes. Controlling access to all the
“pieces and parts” will be a daunting task. Updating and tracking
model changes requires a sound document control protocol to assure all
team players are using the most current version of the model. More
challenging is assigning work packages that allow design teams to work
independently as well as collaboratively while coordinating their
efforts. The BIM gatekeeper must possess the technical and managerial
skills to effectively control model inputs and outputs.
Sharing Model Data – Consultants, contractors, suppliers, and
subcontractors all benefit from sharing project information. The very
value of BIM is predicated on the electronic collaboration using the BIM
model as the central depository for project data. Design professionals,
when asked to provide BIM-related information, should require an
executed disclaimer similar to those currently being used in conjunction
with providing CADD files. There are simply too many unknowns today to
settle for anything less.
As BIM technology advances
and software reliability is tested under the fire of real world
design-construction, more will be known about the quality of the
BIM-generated information.
Software Compatibility – The International Alliance for
Interoperability (IAI) is taking the lead in making design-construction
software work in concert with each other. IAI is closing the gap, but
there is much yet to be done. The risks associated with working across
software boundaries will continue to be a concern for the foreseeable
future.
The Devil Is In The Details – Managing the design process to allow for
adequate detailing and quality assurance/control activities remain the
biggest issues facing design professionals – BIM or no BIM. BIM is not
a panacea for poor project management. Issuing construction documents
without the proper attention to detail and quality reviews is almost
always a function of budget and schedule failures that leave little or
no time and money to do the job right. Sound project management, not BIM
alone, will help solve this all too common problem. While BIM provides
the promise of improved design coordination and fewer field conflicts,
designers must still allocate the required resources to avoid problems.
The cornerstone of any
design firm, whether CADD driven or committed to BIM, is well-trained
people supported by good business practices, sound risk management, and
visionary leadership. There is much more to be written about BIM, its
revolutionary promises, its efficiencies, and its risks. BIM has the
potential of changing the way we all do business.
Gary Prather is the director of Risk Management for the
Architects and Engineers program at Travelers. He can be reached at
816.444.5065 or gprather@travelers.com.
This article is used
with permission by ArchNewsNow.com, see http://www.archnewsnow.com.
It is re-published here in ConstructionRisk.com Report, Vol. 9, No. 8.
Comment by K. Holland – Publisher:
I am pleased to be able to
re-print this important article in this issue of the
ConstructionRisk.com Report because it highlights key issues and urges
the kind of caution I’ve been arguing for in discussions with design
firms that are getting more involved with BIM.
There are significant new risks that need to be taken into
consideration. I
believe that until new risk management techniques have been worked out
and new contract language has been developed to allocate more of the
risk to the project owner and other parties instead of leaving all the
risk with the design firms, BIM poses a serious new risk to design firms
and the insurance carriers that insure them.
At this early point in the adoption of BIM, insurance
carriers may be wondering whether to assign additional costs and premium
for design firms undertaking significant projects utilizing BIM.
This will be an ongoing discussion. At
the upcoming Construction SuperConference being
held in San Francisco, December 12-14 there are three separate sessions addressing BIM.
Based on the speakers and the agenda for these sessions, this may
be a good way to quickly get up to speed if you are interested in
learning more about BIM and project management and risk management
issues surrounding BIM.
__________
Article
3
__________
Surety
Cannot Maintain Negligence Action against A/E for Alleged Failure to
Adequately Inspect and Supervise Contractor’s Work
By J. Kent Holland, Jr.
Where a surety sued a project architect
for alleged failure to adequately inspect and supervise a contractor who
was default terminated due to defective work, the court dismissed the
suit for failure to state a negligence claim upon which relief could be
granted. Although the surety
had no contractual relationship with the architect, it argued that based
on the totality of the circumstances, the architect had a legal duty to
protect the surety against contractor’s defective work and that the
surety was entitled to rely on the architect to conduct proper
inspection and properly supervise that work.
In dismissing the case, the court stated that courts in
Maryland
apply the economic loss doctrine and that in the absence of a contract,
the surety has no basis to recover economic losses.
The duty of an architect to exercise due care in its inspection
services, said the court, extends only “to those persons foreseeably
subjected to the risk of personal injury created.”
Even if the architect had a duty to its client,
Towson
University
, for costs of correcting a dangerous condition created by the
contractor, that duty did not create a separate duty to the surety of
the contractor. RLI
Insurance Company v. John H. Hampshire, 461 F.Supp.2d 364 (D.
Md.
2006).
In this case, RLI Insurance Company
issued a performance bond for a construction subcontractor,
Architectural Facades Incorporated (AFI) to provide indemnity on behalf
of AFI for the benefit of
Towson
University
, the project owner. The
subcontractor fell behind in the performance of installing wall panels.
Eventually, the general contractor declared the sub in default.
AFI then abandoned its work and a default termination was issued.
The subcontractor’s work was completed by another subcontractor
(Hampshire). That work was
inspected by the architect and accepted by the general contractor and
University.
Subsequent to acceptance, however, the
University found that six percent of the panels were not properly
installed and some panels were falling off the building.
All panels had to be removed from the building. The
surety agreed to arrange for this the removal and repair, and engaged
another contractor to perform the work because Hampshire refused to do
it. The surety then sought in this litigation against the architect to
recover its loss on the performance bond.
It argued it was entitled to contribution and common-law
indemnity from the architect. In
reviewing the defense motion to dismiss, the court explained that in
addition to considering the facts in the complaint, it was proper for
the trial court to consider all documents referred to in the complaint
and relied upon by the plaintiff in bringing the action.
(This is significant because it enables the moving party to
include with its motion copies of relevant contract documents as well as
relevant reports that may have been cited in the complaint.)
In
Maryland
, the existence of a legal duty is a question of law to be decided by
the court. There can be no liability in negligence if there is no legal
duty owed by the defendant to the plaintiff.
Moreover, the court explains, “If the risk created by negligent
conduct is no greater than one of economic loss, generally no tort duty
will be found absent a showing of privity or its equivalent.” (citing
Jacques v. First National Bank, 307
Md.
527, 537, 515 A.2d 756 (1986). In
this case, since the surety suffered only economic loss and alleged
neither contractual nor third party beneficiary relationship with the
architect, a tort duty could only exist if the court found there to be
“an equivalent of privity.” The
court here found that the surety failed to plead an “intimate nexus”
between the architect and itself. For
these reasons, the court granted
the motion to dismiss as negligence.
In addition, on the question of contribution and common-law
indemnity, the court dismissed the complaint as being premature because
that is predicated upon a future event which may never occur.
Comment:
I am currently defending a design
professional in a suit in
Maryland
in which the above-discussed case will be cited in our motion to dismiss
for the same reasons successfully argued by the architect in the case
discussed. In our
litigation, the plaintiff asserts it had a contract with the consultant
but it sued for negligence as well as breach of contract. Since the
complaint fails, in our
opinion, to plead sufficient facts to demonstrate that the consultant
owed the plaintiff a duty of
care independent of the contract, we will ask the court to dismiss the
negligence count, and other counts,
as lacking an independent basis and really being nothing more
than a transparent effort to get around the limitation of liability
clause contained in the contract.
As with the case discussed, because the
plaintiff cited the contract and the consultant’s reports in its
complaint, we will be able to reference terms from those documents in
our motion to dismiss – without thereby causing our motion to be
treated as a motion for summary judgment due to relying on evidence that
was not made part of the pleadings. This is important to us because our
typical defense strategy is to seek to knock out as much of a
plaintiff’s complaint as possible on a motion to dismiss without using
anything outside the pleadings or documents referenced in the pleadings.
Whatever remains, if anything, after the court rules on the
motion to dismiss, we then proceed to flesh out through discovery, and
finally file a subsequent motion for summary judgment using evidence
obtained during discovery – including expert witness affidavits and
deposition testimony.
It never ceases to surprise me how
often plaintiffs fail to comprehend the magnitude of their burden of
proof in professional liability cases.
Plaintiffs must present expert testimony to prove that the
consultant failed to meet the applicable standard of care. Merely
proving that the consultant made errors, omissions or mistakes is not
good enough. Only those
acts, errors and omissions that are negligent can be the basis of
professional liability.
I think too many plaintiffs believe
that all mistakes and errors of a consultant entitle the client to
damages. That, however, is
certainly not the law. With
good expert affidavits and testimony for the defense, the court can
grant summary judgment when the plaintiff has not adequately
demonstrated with its own experts that there is evidence that the
standard of care has been violated.
About the author: Kent Holland is a construction
lawyer located in
Tysons Corner
,
Virginia
, with a national practice (formerly with Wickwire Gavin, P.C. and now
with Construction Risk Counsel, PLLC) representing design professionals,
contractors and project owners. He is founder and president of a
consulting firm, ConstructionRisk, LLC, providing consulting services to
owners, design professionals, contractors and attorneys on construction
projects – including assistance with contract drafting, review and
negotiation; change order and claims analysis (preparation or defense);
risk management advice concerning insurance coverage – including
assistance with negotiating and drafting the terms and conditions of
policies and endorsements; advice to insurance underwriters; guidance to
those procuring insurance; change order and claim preparation, analysis
and defense; contract preparation; contract review and contract
negotiation. Mr. Holland is publisher of ConstructionRisk.com
Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 9, No. 8.
__________
RED VECTOR.COM --- ON-LINE COURSES
Do you need year end continuing education courses?
Currently available on-line risk management courses written by
Kent Holland for RedVector
include: ABCs of Time, Goals and Purpose – The Big Picture.
Also available are: Contract Guide for the Design Professional,
Design Build Professional Liability Risk Management and Insurance; Site
Safety Risk and Liability; Risk Management for the Design Professional;
Managing Communication, Documentation and Reports; Insurance for
Design-Build and Complex Projects; Construction Contract Law; Contract
Claims against Design Professionals; Insurance Coverage Disputes; and
Environmental Claims. See http://www.RedVector.com.
______________________
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D. The Report is independent of any insurance company,
law firm, or other entity, and is distributed with the understanding
that ConstructionRisk.com, LLC, and the editor and writers, are not
hereby engaged in rendering legal services or the practice of law.
Further, the content and comments in this newsletter are provided for
educational purposes and for general distribution only, and cannot apply
to any single set of specific circumstances. If you have a legal issue
to which you believe this newsletter relates, we urge you to consult
your own legal counsel. ConstructionRisk.com, LLC, and its writers and
editors, expressly disclaim any responsibility for damages arising from
the use, application, or reliance upon the information contained herein.
Copyright 2007, ConstructionRisk.com, LLC
Publisher & Editor:
J. Kent Holland,
Jr., Esq.
8596 Coral Gables Lane
Vienna
,
VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
_____________________________________________
|