by Michael C. Loulakis
Record Steel and Construction v. United States , 62 Fed. Cl. 508 (2004), provides an excellent example of the evolution of design-build caselaw. The dispute in this case involved whether a design-build contract required foundations to be over-excavated. The design-builder argued that the contract unambiguously made over-excavation a design recommendation – not a design requirement. In the alternative, it argued that if the contract was ambiguous, then the ambiguity was latent and should be construed against the government. The government argued that the contract expressly and unambiguously required the design-builder to over-excavate the foundation. After carefully examining the relevant contract provisions, the United States Court of Federal Claims (“Court of Federal Claims”) found the contract to be latently ambiguous, and saddled the government with the financial responsibility of the over-excavation. [Editor’s Note: This casenote discussion is excerpted from Design-Build Lessons Learned (2004) – See book review above for more details].
The Corps of Engineers (“Corps”) awarded Record Steel and Construction, Inc. (“Record Steel”) an $8.8 million design-build contract for a dormitory at Offutt Air Force Base in Bellevue , Nebraska . Part of the RFP contained a foundation analysis report, with a section entitled “Subsurface Recommendations.” Included in the recommendations was the following language:
Due to the anticipated column loads for a multi-story building, it is believed that improving the site is more viable than reducing the bearing pressure to a very low value …. The recommended improvement program is outlined below.
The recommended program contained statements that materials be undercut and “should be excavated” from below the bottom elevation of all building footings.
In response to the RFP, Record Steel submitted a price proposal informing the Corps that it did not believe over-excavation for the foundations would be required but, if site conditions ultimately required over-excavation, Record Steel committed to perform this work at no additional cost. The need for over-excavation was discussed during several design meetings both prior to and after contract award. The parties agreed that Record Steel’s geotechnical firm was to conduct field investigations and tests and provide such information to both Record Steel and the Corps. If the resulting data was satisfactory, then Record Steel could proceed with its design without conducting over-excavation.
The geotechnical firm concluded that the native soils were adequate to support the building’s footings without over-excavation. However, the Corps apparently re-evaluated its position and refused to issue a notice to proceed for the footings unless Record Steel agreed to conform to “the requirements of the subsurface recommendations of the Foundation Analysis Report” and over-excavate the site. Record Steel complied with this order and submitted a claim for approximately $188,000 for the costs associated with the over-excavation effort.
The Court first looked at the reasonableness of each party’s contract interpretations. In finding that Record Steel’s interpretation was reasonable, it first noted that Record Steel, as the designer-of-record, was expected to exercise its professional judgment in designing the dormitory and had to defer only to specific requirements contained in the RFP, not to recommendations. The Court then examined how the “requirements” in the RFP were expressed in terms of words like “shall,” “may,” and “should.”
It found that the most critical aspects of the foundation report used the word “should” instead of “shall” – and that this expressed a desire for action, but not a binding requirement. It looked to the fact that the foundation report stated that the Corps “believed” that over-excavation was “more viable” to improve the site, and couched its report in terms of a “recommendation” rather than as a requirement. The Court also found Record Steel’s interpretation to be reasonable based on the fact that the Corps’ initial borings were not conducted within the actual footprint of the dormitory’s location.
The Court ruled, however, that the Corps’ contract interpretation fell “within the zone of reasonableness.” It looked to the fact that the RFP used the verb “shall” in connection with incorporating the foundation report’s recommendations into the contract, and that, by referring to the terms “over-excavation and compaction requirements,” there was an argument that the RFP expressly converted the foundation report’s recommendations into requirements.
Faced with two reasonable contract interpretations, the Court then looked to the rule of contra proferentem for guidance on who should bear the risk of these ambiguities. The four-part test associated with this rule places the risk of the ambiguities on the government when: (1) the contract specifications were drawn by the government; (2) the language used therein was susceptible of more than one interpretation; (3) the intention of the parties does not otherwise appear; and (4) the contractor actually and reasonably construed the specifications in accordance with one of the meanings of which the language was susceptible. The Court found that all of these conditions were satisfied.
The court also refused to apply the exception to the general rule of contra proferentem (i.e., the patent ambiguity doctrine), which resolves ambiguities against the contractor where the ambiguities are “‘so ‘patent and glaring’ that it is unreasonable for a contractor not to discover and inquire about them.’” The court did not find this ambiguity obvious, particularly since the Corps had not indicated its view of the mandatory nature of these so-called “requirements” until many predesign meetings between the parties had taken place.
There are several “take-aways” from the Record Steel case. Owners who use competitive procurement processes, like the Corps of Engineers and other public agencies, must remember that proposers get the benefit of the doubt if there is something wrong with or unclear about the owner-furnished RFP documents. The fact that the over-excavation concept was expressed in terms of a “recommended” process started the potential for ambiguity, and the “should,” “may,” and “shall” verbs contained in the foundation report sealed the deal for the conclusion that there was an ambiguity. If the Corps wanted to mandate over-excavation, it should have said so explicitly.
Equally important, however, is that Record Steel did the right thing by advising the Corps during the proposal phase that it did not intend to undercut unless soil conditions required it to do so. These actions demonstrated that Record Steel actually relied upon its interpretation of the ambiguity, which is one of the predicates to recovery under the contra proferentem rule. The result of this case might have been different if Record Steel recognized the ambiguity but never informed the Corps of its interpretation during the proposal process.
ConstructionRisk.com Report, Vol. 7, No. 8 (Dec 2005)
Copyright 2005, ConstructionRIsk.com, LLC
Cases like the above are very frecuent, when design define the footing elevation for an industrial building, even when the geotechnical recomendation,are based on the boring logs indicate the possible elevation for the foundations.
The boring locations profile may varie depending de topography and the formations encountered, and should be addresed on the RFP, indicating that the Soil Mechanic results, only represent the soil formation at the location of the boring, and the elevation of the footings shall be ajusted to the stratum capable to absorb the design loads.
In other words, previous to start the foundation design, the Owner,Engineers, Architects and Contractor should review the “Geotechnical Investigation Result and Recomendations”
The bearing capacity of the soils encountered, will varie, and the SPT(standard penetration test),and Plate load test, will give to all tentative bearing capacity values.