by Kent Holland | Feb 9, 2011 | Newsletter Article
A material factual dispute existed regarding whether an architect met the requisite standard of care in reviewing an engineering report prior to its client’s purchase of property and prior to the architect proceeding with plans for renovation of the building. ...
by Kent Holland | Feb 8, 2011 | Newsletter Article
An architect performed both design and construction administration services under its contract with a school district. When the construction contractor completed the project eight months late, the architect alleged that it was entitled to recover compensation for the...
by Kent Holland | Feb 7, 2011 | Newsletter Article
An architect proved that it was entitled to be compensated for additional services it provided as a result of the construction contractor’s delay in completing work. Due to the delay, the A/E performed extra duties such as responding to questions from subcontractors;...
by Kent Holland | Feb 7, 2011 | Newsletter Article
It is surprising how many cases there are in which a consultant or contractor performs additional services or work for an owner without first adhering to notice and approval requirements of the contract. Failure to obtain authorization for additional work from the...
Connect