by Kent Holland | Feb 9, 2011 | Newsletter Article
by J. Gerard Boyle Claims Analyst and Senior Project Manager Revay and Associates Limited – Toronto Shortly after work commences on design-bid-build projects all over this country, it can be predicted with reasonable certainty that the Owner and/or Consultant will...
by Kent Holland | Feb 7, 2011 | Newsletter Article
Some of the most common disputes in construction cases relate to delay. However, delay claims tend to be some of the least understood and frequently confusing claims in the construction field. A clear understanding of the basic elements necessary to prove delay claims...
by Kent Holland | Jan 3, 2011 | Newsletter Article
A subcontractor sued the general contractor for breach of contract and quantum meruit, and also the contractor’s surety on a Miller Act claim. What the subcontractor sought was payment for unanticipated costs incurred in constructing a federal law enforcement...
Connect