by Kent Holland | Feb 20, 2017 | Newsletter Article
A road contractor’s claim for entitlement to compensation for installing double the amount of fill material than was estimated in the bidding documents by the county engineer was untimely filed after the contract was completed, and when the engineer recommended that...
by Kent Holland | Feb 20, 2017 | Newsletter Article
Where an elevator subcontractor filed a breach of contract claim against the general contractor for damages resulting from delay to the performance of the work, the general contractor moved for summary judgment on the basis that the subcontractor failed to comply with...
by Kent Holland | Dec 19, 2016 | differing site conditions, Newsletter Article
After final payment was made under its contract, a utility construction contractor submitted a written request for additional payment to the project owner seeking payment for extra work it performed as well as increased costs due to delays and disruptions during the...
by Kent Holland | Dec 19, 2016 | Newsletter Article
The “no-voluntary payments” condition of an insurance policy was violated by an insured subcontracting concrete company, when it entered into a settlement with its prime contractor and paid damages for contractual liability for construction delays as well as for an...
by Kent Holland | Sep 1, 2015 | Newsletter Article
Kent Holland, J.D. ConstructionRisk, LLC Where a contractor was late in performance, a town terminated the contract for convenience and subsequently claimed liquidated damages (LDs) against the contractor. Both the trial court and appellate court concluded that the...
Connect