by Kent Holland | Dec 29, 2020 | Newsletter Article
A contract clause making the contractor solely responsible for any changes of whatsoever nature was not ambiguous when it came to the extra costs to change the influent pipe size and design to fit with an “or equal” equipment item submitted by the contractor in place...
by Kent Holland | Jun 16, 2017 | Newsletter Article
By J. Kent Holland, Jr., Esq. Contractor installed pine wood decking renovating the front porch of a historical building. The project owner, who was also an architect, insisted on the use of pine despite the contractor’s “repeated recommendations to use a different...