by Kent Holland | Mar 29, 2013 | differing site conditions, Newsletter Article
Where a contract contained both a differing site condition clause as well as language stating that bidders may not rely upon data (such as soil information) provided by the owner with the invitation for bid (IFB) but should perform its own site investigation instead,...
by Kent Holland | Feb 8, 2011 | differing site conditions, Newsletter Article
Contract provisions requiring contractors to perform site investigation and inspection prior to bidding did not impose the risk of subsurface conditions on the contractor, and therefore, did not preclude a claim for equitable adjustment. When the contractor began...